The EMC project for recovering waste heat from the riser of the 6-meter coke oven at the Coking Plant of Baogang Group in Inner Mongolia has been completed and passed acceptance, and has been put into operation smoothly. It generates superheated steam with a temperature of no less than 220°C and a pressure of approximately 0.6 MPa, with a steam production rate of ≥100 kg per ton of coke.

Release date:

2019-06-25

The EMC project for recovering waste heat from the riser of the 6-meter coke oven at the Coking Plant of Baogang Group in Inner Mongolia has been completed and passed acceptance, and has now been successfully put into operation. It generates superheated steam with a temperature of no less than 220°C and a pressure of approximately 0.6 MPa, with a steam production rate of ≥100 kg per ton of coke.

Steam, rising, coke oven, recovery, generating, waste heat, smoothly, Inner Mongolia, completed